Smooth Ride Home Road Work March 23-27, 2015

As part of the St. Landry Parish Smooth Ride Home rural road improvement program, following is the schedule for road work on Phase 1A and 1B for the week of March 23-27, 2015. The schedule may change based on weather conditions and other conditions beyond the control of the construction company.
 
Monday, March 23rd
Bolden Rd. - shoulder work  
Chanterberry Rd. - pipework 
Dupre Rd. -  pre-paving work and lay asphalt
Hebert Rd - overlay operations
Knott Rd. - overlay operations
 
Tuesday, March 24th
Bolden Rd. - shoulder work  
Dupre Rd. -  pre-paving work and lay asphalt
St. Berchman Rd. - pipework
Ross Rd. – pre-construction work
Hebert Rd - overlay operations
Industries Lane. - overlay operations
 
Wednesday, March 25th
WPA Rd. – Surface dressing
School Rd. – pre-construction work
Dupre Rd. -  pre-paving work and lay asphalt
Babineaux Rd. - pipework
Northwood Rd. - overlay operations
 
Thursday, March 26th
Texas Eastern Rd. – shoulder work
St. Matthew Rd. – lay asphalt
Babineaux Rd. - pipework
Guillory Rd. – pre-construction work
Live Oak Rd - overlay operations
Oscar Rivette Rd. - overlay operations
 
Friday, March 27th
Texas Eastern Rd. – shoulder work
Guillory Rd. – pre-construction work 
Duplechain Rd. - pipework
St. Berchman – lay asphalt
Oscar Rivette Rd. - overlay operations
 
Please don’t hesitate to contact our office if you have any questions or require additional information, 337.948.3688.
Thank you.